NK-33
TwitterFacebookpinterest


Spektr-RG

Spektr-RG home page




Spektr-RG faces more delays

The final assembly of the Russian-German X-ray orbital observatory hit a snag again, forcing a six-month postponement of its launch. In the meantime, preparations for launch bogged down during the first half of the year.

Bookmark and Share

rosita

Spektr-RG project scientists and space officials inspect German-built eRosita telescope at NPO Lavochkin facility in February 2017.

On February 16, NPO Lavochkin, the prime contractor responsible for the development of the Spektr-RG spacecraft, hosted the first meeting of the project team in 2017. According to the company, the German side, which provided one of the two instruments for Spektr-RG, confirmed the successful completion of tests on the eRosita telescope after its delivery to Russia. The German instrument was then expected to undergo entry control by engineers from NPO Lavochkin and Moscow-based Space Research Institute, IKI. Both telescopes of the mission were then slated for electrical tests, which would clear the way for the final assembly of the flight-worthy observatory before its long-delayed launch then planned in March 2018.

However in the subsequent months, work on the Spektr-RG seemingly came to a standstill. During another meeting on May 16, the mission management broke the news that the launch of the Spektr-RG would have to be postponed for another six months from March to September 2018. The main reason for the delay was blamed on a production defect in a component, which prevented the on-time delivery of the onboard radio complex, BRK, for the spacecraft. The delivery of the crucial radio system for the Spektr-RG spacecraft had been repeatedly promised within a month since the middle of the previous year but had been constantly delayed. Although the testing of the spacecraft could be conducted with a stand-in model of the BRK, the work on the telescopes had also remained stalled due to "missing documents," according to Russian officials. As often happens in international projects, translation of documents and language barriers slowed down the work.

In the official interview published on May 18 by TASS and Roskosmos, the head of NPO Lavochkin Sergei Lemeshevsky said, "In particular, it is necessary to re-program the onboard flight control system, because not everything was designed as planned on the eRosita telescope. In addition, it will be necessary to check the new software."

Industry sources explained that Lemeshevsky had referred to an issue discovered last fall during the integrated tests of eRosita. At the time, engineers realized that under some rare circumstances, a main controller failure could lead to the shutdown of the thermal control system in the telescope, if there was no reaction from onboard computers within a few hours. The German team proposed a minor software change in the satellite's flight control system, BKU, which would provide the necessary redundancy by turning the controllers off and on, if they did not respond in a normal fashion.

The software fix would also require some tests of the software after the integration of the eRosita telescope with the Spektr-RG spacecraft.

According to sources at NPO Lavochkin, eRosita also had problems sending scientific data via the BRK radio system during tests. The culprit was eventually traced to a misunderstanding between the Russian and the German team of the jointly agreed transmission protocol. The issue was resolved in April 2016 and the prototype of the eRosita telescope was successfully re-tested in conjunction with the spacecraft. Still, the problem pushed back the completion and testing of the BRK radio system, a source at NPO Lavochkin said. According to Russian sources, the assembly of the BRK was further complicated by organizational problems and by errors during the wiring of electronic boards of the system.

At the time, NPO Lavochkin also faced a 1.4-billion-ruble penalty from Roskosmos for its failure to deliver Spektr-RG on time in accordance with a contract signed in 2011.

Real reasons for the delay

At the May 16 event, the long-delayed delivery of the radio system, BRK, for Spektr-RG was now promised by June 15. In the meantime, a prototype of the BRK was installed on the spacecraft for final tests. In turn, these tests could only begin after the completion of entry inspections on both telescopes, which were not expected to finish until end of May.

At the beginning of July, NPO Lavochkin hoped to resume electric tests of the spacecraft, this time with flight-worthy models of both telescopes and the operational BRK radio system. The delay in the BRK delivery would push the readiness of the spacecraft for launch until June 2018. However, the next available launch window for Spektr-RG dictated by ballistic conditions would not be available for a few more months, hence the new launch date in September 2018.

The cumulative delays in the project required to formally cut the guaranteed life span for the Spektr-RG telescope in orbit from seven years to 6.5 years.

On the bright side, the IKI team reported that the testing of the Russian-built ART-XC telescope had been completed on April 15.

(To be continued)

 

Bookmark and Share

Read (and see) much more about this and many other space developments in Russia
in a richly illustrated, large-format glossy edition:

Book

 

Article by Anatoly Zak; Last update: May 22, 2017

Page editor: Alan Chabot; Last edit: May 19, 2017

All rights reserved

Book

design

General architecture of the Spektr-RG spacecraft as of 2017. Credit: NPO Lavochkin


inspection

An ART-XC telescope shortly after its delivery to NPO Lavochkin at the end of 2016. Click to enlarge. Credit: Roskosmos


e_rosita

The eRosita telescope shortly after its delivery to NPO Lavochkin in January 2017. Click to enlarge. Credit: Roskosmos


to spacecraft home to Phobos-Grunt home to Science spacecraft home to Spacecraft home